Work on multi-use path moves toward Sept. finish

Trail to link mobile-home community with park-and-ride lot.

Crews work on the Blue Star multi-use path on Tuesday, Aug. 13, 2024.

Construction crews are placing pilings, building bridges and moving dirt as they close in on a completion date next month for the new multi-use path along Blue Star Highway in Laketown Township.

Work recently resumed on the just less than one-mile-long path on the south side of the road from the Shangrai-La Mobile Home Community, 6180 Blue Star Highway, to the Michigan Department of Transportation’s park-and-ride site at Exit 41 of I-196, after a delay last year due to higher-than-expected bids.

The previous cost estimate in 2023 was about $1.2 million. The latest estimates are for about $1.1 million.

Much of the funding for the project is coming from grants. 

The project should be complete by the end of September.

Crews work on the Blue Star multi-use path on Tuesday, Aug. 13, 2024.

The construction of this shared use path will help connect a recreationally and infrastructurally underserved area of the township with transportation options and an area-wide path system.

The path links the 66-site mobile home community with the ride-share lot along the expressway so residents can have easier access to transportation.

There are no other Laketown Township multi-use paths east of I-196 where this project is located.

Crews work on the Blue Star multi-use path on Tuesday, Aug. 13, 2024.

The long-term plan for the Laketown Township Blue Star path is to eventually link with a 64th Street path and the Saugatuck Township portion of the Blue Star Trail, a 20-mile paved non-motorized path between Saugatuck and South Haven.

Barrels mark where work will be on the Blue Star Highway path on Wednesday, July 31, 2024.