Installation of new beach stairs underway
Laketown Beach remains closed as work progresses on dune.

The installation of new stairs at Laketown Township Beach, 6710 142nd Ave., continues and will be completed by the end of next month.
Crews from Lakeshore Concepts LLC of Holland began work on Friday, Oct. 9, 2026, by shipping materials to the site by barge.
“They’ve got quite a bit of work yet ahead of them putting on rails and finishing up the project,” Parks and Recreation Commission Chairperson Brad Laninga told the township board on Wednesday, Oct. 14. “We’re excited for how far along things are already in this first week.”
Work will be completed by Nov. 25.
Check out this video of the work. Click here.
The entrance to the beach from the parking lot is blocked by a barricade to keep people away from the construction site. The township asks visitors to stay away from the work zone for their safety and the safety of the workers. Please stay off the sensitive dunes.
“Soon everyone will be able to enjoy those stairs and traverse up and down through the bowl successfully and without short breath,” Laninga said.
The township website offers alternative beach sites here.

History of stairs
The Laketown Township board in May approved spending more than $210,000 for the adjustable aluminum stairs known as EZ Beach Steps. These steps can be raised or lowered as the dune changes.
The previous set of wooden steps, built 32 years ago, was closed in March 2025 due to safety concerns. The steps were removed and new fencing added to keep visitors off the dunes to prevent further erosion at the beach.
The new steps, the first phase of a three-phase project at the beach, extend from the top of dune through an area called “The Bowl” to the beach.
The new steps are north of where the old steps were located and take a more direct route to the beach.
Phases and grants
The township earlier applied for two grants from the Michigan Department of Natural Resources to complete improvements at the beach.
One application is for a $150,000 Passport Grant. The grant would help fund steps at the top of the dune and a 10-foot-by-32-foot viewing platform, benches and signage. It also would pay for dune restoration plantings of grass, trees and shrubs.
The stairs, platform and plantings are Phase 2 of the three-phase project.
The other application is for a $371,200 Trust Fund Grant. The money would help fund Phase 2 except the platform area. It would also include steps from the parking lot up the dune and timber barrier fencing in the parking area and entrance. This is Phase 3.
The township will find out if it received the grants by the end of the year.